AMI Project Insights
MEPCO and PESCO with the help of USAID placed a work order on KBK to install AMR system on turnkey basis with necessary components to build an integrated and complete AMI system in the company.
Total 1587 Smart meters were supplied and installed as billing meters all over the MEPCO and PESCO jurisdiction under this project. After installation and commissioning, a comprehensive training session of MEPCO and PESCO Officials was also conducted.
KBK will provide O&M services for 2 years against this project. Project was completed in 2021.
Core Features of Project
- Supply, Installation and Commissioning of Three Phase Whole Current 3G Smart Meter with Disconnection Relay Qty. 970 Nos.
- Supply, Installation and Commissioning of CT Operated 3G Smart Meter Qty. 617 Nos.
- Supply, Installation and Commissioning of MDC hardware and Software
- Supply of communication services